Murray Force Main Rehabilitation
Completed – Fall 2026
Project background
The Murray Pump Station has two pressurized sewer pipes, also known as force mains. These pipes run parallel under Beach Drive Southwest and help move sewage to West Point Treatment Plant. The sewage is cleaned and safely discharged into Puget Sound there. In March 2022, one of the pressurized pipes broke due to severe corrosion. King County repaired about 800 feet of the damaged pipe at that time.
This project repaired the remaining 350 feet of damaged pipe and installed valves to ensure reliable wastewater service. The work took place during the dry season to avoid service disruptions. The pump station and the force mains returned to operation in fall 2026.
Previous project updates
- Construction is complete! Take our post-construction survey, October 2026
- Lowman Beach Park restoration underway while valve installation continues, September 18, 2026
- Pipe liner installed; work continues near Lowman Beach Park, August 14, 2026
- Sewer work continues near Lowman Beach Park, July 24, 2026
- Coating pump station hatches around June 23 and June 24, June 18, 2026
- Portion of sidewalk to close at Lowman Beach park until August, June 9, 2026
- Sewer work begins June 1 near Lowman Beach Park, May 22, 2026
- Murray Pump Station valve replacement work begins May 1, April 29, 2026
- Thank you for visiting us and taking the Community Survey, April 17, 2026
- Construction near Lowman Beach Park begins in May, April 2, 2026
- Construction near Lowman Beach Park begins in summer 2026, December 2025
Project location
Project phase

Translations
Español (Spanish)
Public Engagement
Date: Wednesday, July 15, 2026
Time: 7 pm to 8 pm
Location: Zoom virtual meeting
Event Summary
The Murray Force Main Rehabilitation Project team attended the Morgan Community Association’s (MoCA) July 15 meeting via Zoom to provide a briefing on the project and respond to questions about restoration plans at Lowman Beach Park.
Outreach Events
Dates:
Monday, April 6, 2026, 3 to 6 pm
Friday, April 10, 2026, 11 am to 2 pm
Sunday, April 12, 2026, 3 to 6 pm
Location: Lowman Beach Park
The project outreach team hosted three drop-in sessions at Lowman Beach Park to introduce the project to interested community members and answer construction questions.
Translate