Baring Bridge Replacement Project

Temporary bridge opened to traffic on August 6, 2026

Temporary Baring Bridge opens.

August 6, 2026: The temporary Baring Bridge opened to the community after roughly four months of construction

Status update

August 7, 2026

Baring Bridge Construction Completed
On Thursday, August 6, 2026, crews completed construction of the temporary Baring Bridge on NE Index Creek Rd between 641st Ave NE and 639th Ave NE. The bridge is now open to traffic.

Work on the temporary bridge, located just downstream from the historic Baring Bridge over the South Fork Skykomish River, began on April 6, 2026, after December 2025 storms and flooding severely damaged the timber structure, and a decreased load limit was put in place. The restriction limited access to emergency crews, utility workers, and essential deliveries such as propane and septic services. Crews worked diligently to complete this project as safely and efficiently as possible, and we appreciate the community’s partnership and patience during construction.

The newly constructed temporary bridge does not have a posted weight restriction. All legal loads are allowed.

The historic timber Baring Bridge is now closed to all vehicular traffic. It will close to pedestrian traffic on September 30, 2026.

King County is also planning a permanent bridge replacement, with a wider, steel truss bridge. Construction for the permanent replacement is anticipated to begin in 2029 and last through 2031.

Community Celebration – September 12, 2026

King County Road Services is planning an event on September 12, 2026 to celebrate the historic timber bridge before it is removed.

September 12, 2026, from 10:30 am to 12 pm at the new temporary Baring Bridge

The celebration will include:

  • A guided historical tour at 11 am
  • Fun mementos (limited quantity)
  • Snacks and light refreshments

Join us to honor a beloved piece of Baring's history!

The community can stay informed about this project by visiting this website, subscribing to Road Alerts in the Skykomish Area and using the MyCommute Map.

Project location

Vicinity map for the Baring Bridge project location.

Baring Bridge is a King County owned and maintained timber suspension bridge. It is located on NE Index Creek Road over the South Fork Skykomish River near the Town of Baring and U.S. Route 2.

Temporary bridge project overview

King County worked quickly to restore safe access and important services for people living in Baring, WA after storms and flooding in December 2025 damaged roads and bridges throughout Western Washington. To help right away, the Department of Local Services’ Road Services team and the County’s Finance and Business Operations Division fast-tracked a construction contract to build a temporary bridge while waiting for the permanent replacement of the existing bridge. This temporary bridge is also needed for the construction of the new bridge for construction vehicles to access the far side. This bridge is located just downstream from the historic Baring Bridge over the South Fork Skykomish River. The river crossing is the only way to reach about 170 properties.

The historic Baring Bridge was badly damaged during the storm. Road Services crews cleared logs and made small repairs after several trees hit the bridge, but only vehicles under 5 tons (10,000 pounds) were able to use it. This limited access for residents, emergency crews, utility workers, and essential deliveries of things like propane and septic supplies. The new temporary bridge will allow heavier vehicles reach the community.

The temporary bridge was installed in spring/summer 2026. . Crews began work on April 6 and completed construction on August 6, 2026. The project was built by Johansen Construction Company of Sumner, WA. King County is also planning a permanent replacement for the historic Baring Bridge which is expected to begin in 2029.

Temporary bridge design

The new temporary bridge is an Acrow Bridge and is a high-strength, prefabricated modular steel bridge designed for rapid assembly and versatility in permanent, temporary, or emergency applications. It was manufactured in the United States.

The temporary bridge is wide enough to accommodate one direction of vehicular traffic and pedestrian access at the same time.

Temporary bridge over a creek in Cordova Alaska

The temporary bridge looks similar to this photo of an Acrow bridge in Cordova, Alaska.

Permanent replacement bridge project overview

The Baring Bridge provided sole access to approximately 170 properties, including more than 40 residences, in the unincorporated community of Baring, WA. Much of the historic timber bridge was repaired or retrofitted over the years, however it has continued to decay and must be replaced. King County will replace the timber bridge with a wider, steel truss bridge. The new bridge will be open to all vehicles and carry no weight restrictions. Construction for the permanent replacement is anticipated to begin in 2029 and last through 2031.

Baring Bridge over the south fork of the Skykomish River.

The historic Baring Bridge was built in 1930. In 1999, it was designated a Landmark by King County and in August 2019, the bridge was listed on the National Register of Historic Places.

Permanent replacement bridge design

The new permanent Baring Bridge will be a steel truss bridge. It will be built in the same location as the historic timber bridge. The new bridge will be open to all legal loads and sizes and types of vehicles. It will be 24’ wide curb to curb.

Drawing of the new bridge design.

  • Painting the steel truss “National Park Service Brown,” so that it blends in with the scenery.
  • Incorporating weathered steel railings on the bridge and approach to better fit the rural character of the setting.
  • The new bridge foundation will be located out of the ordinary high-water mark and will be on deep foundations to provide scour protection.

Baring Bridge, existing condition.

The weight restriction on the historic Baring bridge (above) was five tons (10,000 pounds). The steel truss replacement bridge will not have a vehicle weight restriction.

What to expect during construction of the permanent bridge

Construction for the permanent structure is currently planned to start in spring 2029 and end in fall 2031. In summer of 2026, King County completed installation of a temporary one-lane bridge adjacent to and downstream of the existing bridge. The temporary bridge will carry traffic over the South Fork Skykomish River until construction can begin and while the permanent bridge is under construction.

Community involvement

A community meeting was held on Saturday, March 28, 2026, for neighbors to learn more about the installation of the temporary bridge. The slide deck for this meeting can be found in the public outreach section of this website.

Public engagement with community members about the replacement Baring Bridge project began in January 2019. Since then, we have held several community meetings, presentations and workshops. We've used input from residents, visitors, local businesses, county representatives, state and national agencies to help design the replacement bridge. The project team will continue to work with the public and partner agencies until the new bridge is officially complete. A detailed listing of our public engagement materials, activities and presentations is available in the public outreach and documents section of this website. Community members are welcome to contact us directly for more information or to schedule a meeting.

People in room attending open house meeting.

Road Services held the first Baring Bridge Replacement Project open house in January 2019. The open house was held in the King County Fire District 50 station near the Baring Bridge.

Project documents

Project documents are added to this website for public view. Please read below to see the:

Frequently asked questions about the selected preferred alternative

The new bridge will be built in the approximate same location as the historic bridge.

The Baring Bridge is listed on the National Register of Historic Places. The National Register of Historic Places is governed by federal and state laws and regulations. King County must follow specific rules to decommission, remove and replace a bridge or any other property that is listed on or has been determined eligible for the National Register of Historic Places.

Federal and state laws require mitigation for the removal and replacement of the bridge. Mitigation is a list of agreed-upon actions or commitments designed to help compensate for possible environmental impacts caused by the removal and replacement of the bridge. In this case, the U.S Army Corps of Engineers is responsible for determining the proposed mitigation plan. Next, the Corps works with the Washington State Department of Archaeology and Historic Preservation to make sure both agencies agree on the proposed mitigation plan. Once the agreement is finalized, the Corps will publish a document called the Memorandum of Agreement. This Memorandum is necessary to allow the county to remove the historic Baring bridge.

  • Vehicular use of the historic Baring Bridge is no longer allowed. All vehicles must use the temporary Baring Bridge.
  • The historic bridge will be kept open for pedestrians use through September 30, 2026. It will permanently close to pedestrians prior to winter.
  • The historic bridge will undergo an inspection in August 2026. If this inspection identifies additional structural issues that make the bridge unsafe to cross, pedestrian access will be closed immediately.

King County Road Services is planning an event in September to honor and celebrate the historic timber bridge before it is removed. More information will be available soon.

The Baring Bridge is listed as a King County Landmark. To remove the bridge, Road Services applied for permission from the King County Landmarks Commission. The Landmarks Commission reviewed our application and provided a public comment period. Following the review and public comment process, the Commission granted Road Services permission with a "Certificate of Appropriateness" on March 4, 2025. This certificate is what Road Services needs to move forward. 

King County engaged with a team of engineering and environmental experts and community members to help select the final design of the new bridge. The experts and the community members were provided with several bridge design alternatives and asked to provide their input according to what was most important to them.

An inclusive team of experts met to discuss, evaluate and score all the proposed design alternatives. The experts included specialists from a variety of fields: Engineering, permitting, environmental, property right-of-way, and bridge construction. Next, the team engaged with community members to find out what was most important to the community, and to receive input, comments and questions about the proposed bridge design alternatives. The total scores of each design alternative along with input from the community were reviewed, analyzed and finalized by the Director of King County Road Services, the County Road Engineer and the Engineering Section Manager.

The final design, permitting, and necessary land purchases are expected to be complete in late 2028. We originally planned to complete all the design, permitting and right-of-way work in late 2023. However, it is taking longer than anticipated to obtain the necessary federal and local permits needed to finalize the design and start construction of the permanent bridge.

We intend to advertise the project to potential contractors in winter  2028. Construction is expected to start in spring/summer 2029 and end in spring 2031.

Yes. Approximately 70 trees were removed early in the temporary bridge construction process.

  • Within the riverbank, only the area where the bridge foundation was placed had all trees entirely removed. In the immediate nearby riverbank areas, as few trees as possible were cut to perform the work, but their roots were left in place to continue to hold the riverbank in place.
  • Scour protection, mainly rock, was added around the bridge foundation to stop the soil from washing away and protect the bridge.
  • During construction, workers will use tools like silt fences, straw, and coir logs to control erosion.
  • The land beyond the riverbank was cleared for construction, and all bare soil was covered with seed and mulch for long-term erosion control until the permanent bridge project occurs.

The weight restriction on the historic timber bridge was five tons (10,000 pounds). The weight restriction was reduced in January 1995 and further reduced after a major storm in December 2025. The bridge had a posted speed limit of five miles per hour.

The temporary bridge does not have any weight restrictions. The permanent bridge will also not have any weight restrictions, once it is constructed. All legal loads are allowed.

Yes. A temporary bridge was built adjacent to and downstream of the existing bridge for public use until the permanent structure is complete.

Community members are always welcome to contact the project team. You can email our communications manager at abresslour@kingcounty.gov or call 206-477-9223.

Photos

August 6, 2026: The newly opened temporary Baring Bridge.

 

South approach of the bridge.

July 31, 2026: The south approach of the bridge with the foundation blocks, rock for scour protection, structural earth wall, barriers and steel trusses in place.

 

Repaving work on 639th.

July 28, 2026: Crews repaving 639th Ave NE with hot mix asphalt.

 

Guardrail is installed on the temporary bridge.

July 14, 2026: Crews are installing guardrail to the temporary bridge.

 

The bridge deck is installed.

July 13, 2026: Temporary bridge deck installation.

 

Stabilized earth wall construction.

July 8, 2026: Crews are constructing a stabilized earth wall, a reinforced structure designed to support the bridge.

 

Pouring concrete in the bridge abutments.

July 3, 2026: Contractor crews working for King County are pouring concrete in the bridge abutments, which are strong supports at each end of a bridge that act like anchors to keep the structure stable.

 

Maintenance crew working on bridge at edge of water

June 23, 2026: Crews are launching the final sections of the temporary bridge across the South Fork Skykomish River. 

 

Heavy machinery next to bridge

June 17, 2026: Crews are assembling additional sections of the temporary bridge. 

 

Crew members working on bridge wall

June 15, 2026: Crews are assembling a “structural earth wall” on the south end of the project site. This will provide structural support to the temporary bridge. 

 

Crews working on new baring bridge

June 11, 2026: An excavator operator is “launching” sections of the temporary bridge over the South Fork Skykomish River. 

 

Bridge over water

June 11, 2026: A section of the temporary bridge that crews launched over the river.  

 

 

Temporary bridge being installed

June 2, 2026: The temporary bridge is starting to take shape as crews assemble it over the South Fork Skykomish River.

 

Temporary bridge nose being installed

June 2, 2026: Crews are installing a temporary bridge “nose” to front of the bridge to help guide it as they slide remaining bridge pieces in place over the river.

 

Temporary bridge nose being installed

May 29, 2026: Crews are installing a temporary bridge “nose” to front of the bridge to help guide it as they slide remaining bridge pieces in place over the river. 

 

3 crew members working on concrete slab

May 26, 2026: Crews are putting together roller pads, cushion-like supports which will serve as wheels while crews push the bridge sections in place. 

 

Heavy machinery pouring concrete along river bank.

May 22, 2026: Crews are pouring concrete into the bridge structure to help strengthen and stabilize the bridge.

 

Crews on river bank installing steel piles

May 19, 2026: Crews are installing steel sheet piles, which will protect the bridge foundation and keep the structure in place during and after construction.

 

Maintenance workers installing sheet piles

May 19, 2026: Crews are installing steel sheet piles, which will protect the bridge foundation and keep the structure in place during and after construction. 

 

Concrete truck and workers pouring concrete

May 19, 2026: Crews are pouring and finishing the concrete launch pads on the north end at the project site, where the temporary bridge will later be installed.

 

Maintenance workers pouting and finishing concrete on riverbank

May 19, 2026: Crews are pouring and finishing the concrete launch pads on the north end at the project site, where the temporary bridge will later be installed. 

 

Gravel Borrow in bridge foundation

May 12, 2026: Crews are installing gravel borrow, a type of soil, around the bridge foundation to stabilize it. 

 

Maintenance workers and heavy machinery along river

May 8, 2026: Crews are installing scour protection along the foundation. These large and durable rocks will prevent the removal of sediment around the foundation, typically caused by fast-moving water.

 

Crews using heavy equipment to place large blocks

May 7, 2026: Crews are installing ekoblocks, which form the foundation of the temporary bridge structure. 

 

Maintenance crew member spreading concrete

May 1, 2026: Crews are pouring concrete into the bridge structure foundation to create a stable surface for the next phase of construction of the temporary bridge.

 

Construction crane removes concrete blocks from flatbed

May 1, 2026: Crews unload ekoblocks, large blocks which will be installed as part of the new temporary bridge structure.

 

Sheet piles being installed on hillside

April 30, 2026: Contractor crews working for King County are installing sheet piles that will support the foundation for the temporary bridge. 

 

Crews at work relocating utilities.

April 7, 2026: Contractor crews working for King County are relocating utilities and preparing the site for installation of the temporary bridge.

 

 

April 7, 2026: A video showing our crew driving over the existing Baring Bridge. Currently the existing bridge is weight restricted; however both the temporary bridge and the new permanent bridge will not have any weight restrictions. 

 

People sitting in chairs during community meeting

March 28, 2026: Baring neighbors gathered for a community meeting with members of the project team to learn more about the installation of the temporary bridge. 

 

Tree damage to the Baring Bridge.

December 2025: The Baring Bridge was badly damaged during the storm. Road Services crews cleared logs and made small repairs after several trees hit the bridge.


Trees on the Baring Bridge.

December 2025: Road Services crews worked quickly to clear fallen logs and make temporary repairs after several trees struck the bridge.


Baring Bridge.

Baring Bridge over the South Fork Skykomish River.