NE 128th Way Culvert (Fish Passage) Replacement Project

NE 128th Way, just west of Avondale Road NE, reopened to all travelers on November 18, 2026.

Completed Culvert.

Crews completed construction of the NE 128th Way Culvert Replacement Project on Wednesday, November 18, 2026.

Status update

November 18, 2026

King County crews reopened NE 128th Way, just west of Avondale Road NE, on Wednesday, November 18, 2026, after completing the culvert replacement project.

We are grateful to the community for their patience throughout construction. The new structure improves long term safety and reliability for all travelers.

In the coming weeks crews will continue low impact restoration work including planting and site clean-up, however we do not anticipate an impact to traffic.

Project overview

King County replaced an old, worn-out metal pipe under NE 128th Way near Avondale Road NE with a larger concrete box culvert. The previous metal pipe was rusted and old and could have collapsed. If it failed, the force and volume of the water could have washed out the entire roadway completely, leading to a sudden, long-term road closure for emergency repairs.

Rusty metal culvert with water running through and plant debris on the side.

A closer look at the metal culvert that carried an unnamed tributary stream to Cottage Lake Creek under NE 128th Way. Rust had eaten away at the bottom of the pipe and it was time to be replaced.

The new box culvert makes it much easier for fish in Cottage Lake Creek to migrate to the Sammamish River. Designed to simulate a natural stream, the new culvert maintains a consistent, gentle water flow under the road.

Project location map

Map graphic of project location

This project was located near the intersection of Avondale Road NE in Cottage Lake, near Redmond, WA.

Why did King County replace this culvert?

We are replacing the narrow metal culvert because it is too small, deteriorated, and is a fish passage barrier.

We replaced the narrow metal culvert because it was too small, deteriorated, and at risk of failure. It was also a fish passage barrier.

The new, wider concrete box culvert was designed to improve fish passage under the road. The previous metal pipe was considered a fish passage barrier for two main reasons:

  • It was too small to handle the stream’s water volume, causing fast-moving currents that made it nearly impossible for fish to swim through.
  • At times, the water inside was too shallow in summer months, and the previous culvert sat too high above the stream bed, preventing fish from jumping in and continuing upstream.

Benefits of the concrete box culvert

The new concrete box culvert makes it much easier for fish in the unnamed tributary stream to Cottage Lake Creek to pass under the roadway and continue their migration to the Sammamish River. It was designed to simulate a natural stream and maintain a consistent, gentle water flow under the road. The box culvert can accommodate a much larger volume of water.

Fish have a hard time migrating upstream if there is not enough water in the culvert or if the culvert is perched too high above the stream. The new box culvert makes it easier for fish to pass under the road. (Image courtesy of King County Fish Passage Restoration Program).

The following fish species are found in Cottage Lake Creek:

  • chinook salmon
  • sockeye salmon
  • kokanee salmon
  • coho salmon
  • cutthroat trout
  • steelhead trout

Culverts can block fish migration if the water flow is too swift, too shallow, or if there’s a waterfall entering or exiting the culvert. The new box culvert was designed to maintain a natural flow of water, simulating natural stream conditions. (Image courtesy of WSDOT Fish Passage Program).

Project timeline

  • Final project design: Spring 2026
  • Construction start date: August 17,  2026
  • Substantial construction complete: November 18, 2026

Frequently asked questions

After construction began, crews identified additional drainage improvements needed at a second location just east of the culvert replacement. To minimize future disruptions to travelers, crews completed the additional work during the project rather than returning later and requiring a separate closure.

An road closure was necessary because NE 128th Way is too narrow to safely accommodate the large crane and other equipment required for construction while maintaining traffic through the work zone. The roadway also lacks shoulders for staging equipment and materials.

Twenty-three alder trees and some shrubs were removed as part of this project. All vegetation will be replaced, and the area will be restored. Some of this restoration work will occur after construction is completed.

A fish passage barrier is any obstacle that prevents fish from moving upstream or downstream.

Most fish barriers in unincorporated King County are large round metal pipes (culverts) that direct streams and water beneath roads. Many of these culverts were installed 30 to 100 years ago. These older metal culverts allow water to flow, but they are often too narrow and steep, making it difficult for fish to swim through. 

Culverts may block fish migration if the water flow is too swift, too shallow, or creates a waterfall at the entrance or exit.

This project was in the Bear Creek Basin of the larger Lake Washington/Cedar/Sammamish watershed that contains many miles of high-quality aquatic resources and is known to support a wide range of fish. Replacing this fish passage culvert adds to these valuable resources for aquatic life.

The ability of salmon and trout to swim upstream to their traditional spawning grounds is vital to their recovery across Washington and King County. Deteriorating culverts and other barriers block fish passage and undermine the state and county recovery efforts.

One of the most effective ways to ensure the survival of native fish – and the southern resident orcas that rely on them as a food source – is to remove barriers to their habitat.

The previous metal pipe culvert was rusted and old and needed to be replaced before it failed. If the pipe collapsed the force and volume of the water could have caused the entire roadway to fail.

Prior to construction, the Washington Department of Fish and Wildlife (WDFW) classified the stream as "fish-bearing," meaning it was either inhabited by fish or had the potential to support fish if certain barriers to passage were removed. Because of this classification, the culvert was replaced with a larger concrete box culvert system designed to improve fish passage and support the long-term health of the ecosystem.

During the fish exclusion process, the environmental team temporarily diverted the stream to create a dry work area for construction. Team members then collected and safely relocated aquatic species downstream before construction began. During this process, they identified several salmonids, including cutthroat trout.

This project was part of the county’s Fish Passage Restoration Program. 

 

The new concrete box culvert is 11’ wide by 9’ tall and 68’ long.

Photos

Newly installed guardrail

 November 12, 2026: Newly installed guardrail on NE 128th Way, just west of Avondale Road NE.

 

Crews pouring concrete

October 22, 2026: Crews pouring concrete to re-pave the southbound lane on NE 128th Way. Crews also plan to install guardrail along the roadway to further improve safety for vehicles, pedestrians, and bicycles.

 

Newly installed culvert with fresh plantings

October 13, 2026: The outlet of the newly installed box culvert. Crews have also completed plantings along both sides of the culvert as part of site restoration.

 

Crews lowering sections of the new culvert into place.

September 24, 2026: Crews are lowering the top sections of the culvert, called the culvert lids, into place.

 

Large ditch with concrete walls and segments

September 9, 2026: The sides of the new concrete box culvert have been installed.

 

Crane lowering large concrete slabs on job site

 September 9, 2026: The sides of the box culvert are carefully being moved into place with the help of a crane.

  

Heavy machinery and tarps on a worksite

September 3, 2026: Using a excavator, crews scraped away the earth to make space for the foundation of the box culvert. Plastic sheets were temporarily added to protect the area from rain.


Water pooled in excavation site

September 1, 2026: Site excavation is underway to prepare the foundation of the site for box culvert installation. 

 

Crane carrying trench box

August 27, 2026: A trench box was installed, which will be used later in the project to relocate the waterline. 

 

Pipes going under ground at worksite

August 25, 2026: Crews have installed pipes to divert the stream, so the work area remains dry.

 

Trout in fish measureing container

August 21, 2026: This small cutthroat trout is one of several salmonids found during the fish exclusion process. During this work, environmental teams temporarily divert the stream to create a dry area for construction. As part of the process, they collect any aquatic species and relocate them safely downstream.

 

Metal pipe culvert coming out of the ground among plants.

The previous metal pipe culvert outfall was too high (perched) above the stream bed for salmon and other fish to pass through.