M Street Trunk rehabilitation
The M Street Trunk Rehabilitation Project will repair about 2.6 miles of deteriorated sewer pipes in the City of Auburn.
Project description
The M Street Trunk Rehabilitation Project will repair approximately 2.6 miles of severely deteriorated 18, 24, 30, and 36-inch-diameter reinforced concrete pipe that has more than 100 side sewer connections to nearby properties. The project will also rehabilitate 45 precast maintenance holes.
Active construction is anticipated to occur during the summer window (May to October) of 2025 to 2026 when the wastewater flow is lower.
The design and construction of the project are divided into two phases with Phase 1 construction scheduled for Summer 2025 and Phase 2 for Summer 2026.
- Phase 1 construction covers about 0.6 miles of the trunk covering zone 18, zone 24 and some sections of zone 30 starting from the intersection on 14th Street Northeast to south of 22nd Street Northeast.
- Phase 2 design and construction covers about 2 miles of the trunk covering the remaining portion of Zone 30 and the full length of zone 36.
- The map that follows displays the zones and year of construction.
The M Street Trunk pipe serves a densely populated area with many schools, homes, and businesses in the City of Auburn. During construction for the project, there will be impacts to the travelling public including detours, temporary lane closures, and bus stop impacts. Additional impacts may include on-street parking restrictions, and noise and odors from the diversion pumps. This project may include overnight work. We will share more details as plans develop and will keep the community informed.
Project update
In June 2026, crews began the second phase of the M Street Trunk Rehabilitation Project. Crews are repairing about 1.9 miles of sewer pipe serving the city of Auburn during this phase. Work is taking place between the intersection of 2nd Street Northeast and Pike Street Northeast and 23rd Street Northeast, near the Auburn Municipal Airport (Zones 30 and 36).
November 6, 2026
Overnight work at the Auburn Municipal Airport, November 9-23
As early as Monday, November 9, crews will begin working overnight at the Auburn Municipal Airport near 22nd St. N.E. and E St. N.E. They will repair the sewer pipe, remove the temporary sewer bypass pipe, and restore the roadway. We expect to finish these activities by Monday, November 23. The schedule may be subject to change.
Work will take place at night between 6 pm and 6 am. This is to reduce impacts on the airport, traffic, and nearby businesses during the day.
Flaggers will guide vehicles and help traffic move in both directions near the work area.
What to expect during this work
- Night work will occur within permitted hours between 6 pm and 6 am.
- You will be able to use your sinks, toilets, and showers normally.
- Crews will maintain driveway access.
- Expect noise from trucks, generators, cranes, bucket trucks, and other construction equipment. Lights will be used to illuminate the work area.
- There will be temporary lane and sidewalk closures. Please follow directions from flaggers and posted detour signs.
- Restricted street parking along the temporary sewer diversion pipe and repair work areas.
Stay safe! Please watch for equipment in the area. Travel slowly. Follow signs and directions from flaggers in the work zone.
Phase 2 Sewer pipe repair in your neighborhood starts June 2026
Leer este correo electrónico en in Español (Spanish) | 阅读此电子邮件 (Chinese, Simple) | Прочитайте это письмо на русском (Russian)
As early as June 2026, crews will begin the second phase of the M Street Trunk Rehabilitation Project in Auburn. Learn more about what you can expect during construction.
Learn more
To learn more about the upcoming construction and its impact by work zone, read the latest fact sheet and frequently asked questions.
Visit the online open house for information on the project.
Para obtener más información sobre este proyecto y sobre las próximas obras, visite PublicInput.com/M-Street-Trunk-es o escanee el código.
Чтобы узнать больше об этом проекте, включая информацию о предстоящем строительстве, посетите PublicInput.com/M-Street-Trunk-ru или отсканируйте QR-код.
欲了解更多有关该项目的信息,包括对即将开始的施工的预期,请访问 PublicInput.com/M-Street-Trunk-zh 或扫描二维码。
Sign up for project updates
Subscribe for project updates by email or text to get updates, surveys, notices, and other information by email and/or text. You can unsubscribe anytime.
Past project updates
- Around-the-clock sewer pipe relining work from October 26 to November 5, October 22, 2026
- Around-the-clock sewer pipe relining work October 6-21, October 2, 2026
- Around-the-clock sewer pipe relining work moved to September 21-30, September 17, 2026
- Nighttime waterline relocation on E Street Northeast and 23rd Street Northeast September 8-30, September 4, 2026
- Around-the-clock sewer pipe relining work moved to September 8-19, September 4, 2026
- Around-the-clock sewer pipe relining work extended through September 5, August 31, 2026
- Around-the-clock sewer pipe relining work from August 24 - 29, August 20, 2026
- Around-the-clock sewer pipe relining work from August 17-22, August 13, 2026
- Overnight work: Crews to install temporary sewer diversion pipe August 10 - 28, August 7, 2026
- Utility survey work starting July 14, July 13, 2026
- Overnight work: Crews installing sewer diversion pipe, July 13-17, July 9, 2026
- Driveway closure at E and D Streets NE intersection overnight on Wednesday, July 15, July 9, 2026
- Utility investigation work starts, Wednesday, June 10, June 22, 2026
- M Street project staff at Auburn Farmers Market on Sunday, June 14, 2026, June 10, 2026
- Road restoration work starting as early as March 27, March 26, 2026
- ADA’s compliant ramps and sidewalk upgrades starting as early as March 19, February 17, 2026
- Nighttime M Street Trunk sewer pipe and maintenance hole repair work starting February 17 through 20, February 13, 2026
- Nighttime temporary sewer diversion pipe removal January 29, January 28, 2026
- M Street Trunk sewer pipe and maintenance hole repair work moved to December 10 and 11, December 8, 2025
- Soil investigation work near the M Street Trunk sewer pipe starting as early as December 2, December 1, 2025
- Nighttime M Street Trunk sewer pipe and maintenance holes repair work, November 17 through November 26, November 14, 2025
- Limit water usage from 7 am on Monday, November 10, to 7 am on Tuesday, November 11, November 7, 2025
- Limit water usage on Thursday, November 6, between 7 am and 9 pm, November 6, 2025
- Nighttime sewer pipe repair work November 5 and 7, October 31, 2025
- Nighttime M Street Trunk sewer pipe and maintenance holes repair work, October 27 through November 7, October 23, 2025
- Nighttime temporary sewer diversion pipe installation work, October 9 though 11, October 2025
- Installing temporary diversion pipe and pumping system, September 2025
- Construction starting near you in late August 2025, August 2025
- Visit our online open house for upcoming wastewater project, June 2025
- Utility investigation work starts April 14, April 7, 2025
- Construction starting Summer 2025, March 2025
- Surveying work starts December 16 continuing through December 20, 2024, December 11, 2024
- Soil surveying work starts November 18, 2024, November 2024
- Utility investigation work starts on October 28 continuing through November 8, October 2024
- Survey work for M Street Trunk Rehabilitation Project begins July 2, July 1, 2024
- Survey work for M Street Trunk Rehabilitation Project begins June 25, June 25, 2024
- New King County project coming to your neighborhood, Winter 2024
Interactive construction map
The interactive construction map below shows active construction updates where temporary pipes, road, equipment staging and other construction activities in the project area.
Translate
